The review meeting for the drawing has started. The project is a 132 kV solar farm in the Middle East, and the room is discussing a selection of substation transformers of 40 MVA. The EPC contractor has sent a datasheet, the owner's engineer is chall...
VIEW MORE
During the commissioning of a 2,000 kVA substation installed on the intermediate mezzanine floor of a regional medical center in Chicago, facility operators immediately raised an alarm. Even though the unit met nominal factory baseline tests, the con...
VIEW MORE
When specifying medium-voltage distribution equipment for commercial developments, renewable energy sites, or utility grids, one of the most critical decisions confronting electrical engineers is the selection between dead front and live front compar...
VIEW MORE
Last November a 2,000 kVA cast-resin unit was set on its pad outside Johor Bahru with a complete document package — UL label, CSA mark, routine test report, winding resistance figures. Ninety minutes after the contractor closed the main breaker...
VIEW MORE
A developer in Houston sent the same 1500 kVA, 13.8 kV to 480Y/277 V specification to four suppliers last spring. The quotes came back between $38,400 and $61,900 for what the drawings called an identical unit. All four bidders held a UL listing, all...
VIEW MORE
A consultant in Johor specified 630 kVA, 11 kV to 433 V, 50 Hz, 4.5% impedance. A US integrator read the same 600 kVA load schedule and ordered 750 kVA, 13.8 kV to 480Y/277 V, 60 Hz, 5.75%. Both engineers were correct. The trouble started three weeks...
VIEW MORE
The label on the switchboard said 8 cal/cm2. The study behind it had been run against a 1,500 kVA transformer at 5.75% impedance, a unit that was pulled out eighteen months earlier and replaced with a 2,000 kVA unit carrying the same nameplate impeda...
VIEW MORE
Two quotes for a 2,000 kVA unit landed on a buyer's desk in Houston in July. The lower bid won by $9,800. Nine months later the finance team pulled the guaranteed losses out of the approved submittal and ran the numbers again: at 8,760 hours a year, ...
VIEW MORE
An inspector stops the sign-off on a new 1,000 kVA unit because the neutral is landed on the enclosure ground bar, the green bonding screw is still in its factory position, and a bare copper conductor runs from X0 to the building steel. Each detail l...
VIEW MORE
A data centre contractor in Johor sent us a load schedule last year with a single number on it: 10 MVA, continuous. His incoming oil immersed transformer had arrived with a nameplate reading ONAN 8,000 kVA / ONAF 10,000 kVA — the transformer co...
VIEW MORE
The failure of a heavy duty substation transformer also comes at a cost beyond repair hours. It is quantified in dark data centers, dead production lines and lost delivery windows. Ryan Electric, a joint venture with Eaton (USA), manufactures dry-typ...
VIEW MORE
The tender arrived as twenty pages of civil works and one line of electrical scope: supply and install 6.6 kV shore power. We asked the port's electrical engineer what frequency the visiting fleet ran on. There was a pause, then the an...
VIEW MORE